Ongoing Projects

Project Description

School Name

District

Status

Notes/Updates

Gymnasium Renovation

Claude O Markoe

St. Croix

In progress

3/13/2025 awaiting bleacher delivery 2/19/2025 Bleachers removed, new interior lights are being installed. New bleacher ordered, pending delivery and installation.

Kitchen Renovation Supplemental

Claude O Markoe

St. Croix

In progress

2/19/2025 original contract work 90% completed.

Kitchen Renovation Supplemental 1

Claude O Markoe

St. Croix

In progress

2/19/2025 30% complete. Awaiting walk in-coolers and freezers, prep tables and a roll-up door.

Kitchen Renovation

Eulalie Rivera

St. Croix

On hold

2/19/2025 Project on hold due to contractor's noncompliance with documentation request and contract terms.

Kitchen Renovation

St. Croix

Basketball Court Resurfacing

Pearl B. Larsen, Ricardo Richards, Alfredo Andrews, Eulalie Richards, Lew Muckle

St. Croix

In progress

2/19/2025 Completed; Lew Muckle, Eulalie Rivera, Pearl B. Larsen, In Progress; Ricardo Richards Pending RFI/ Change order review; Alfredo Andrews.

Generator Purchase and Installation

Bertha C. Boschulte

St. Thomas

In progress

2/19/2025 Generator is on order. Change order was issued for time. DPP is also creating another contract.

Generator Installation

Bertha C. Boschulte

St. Thomas

In progress

2/19/2025 Contractor is awaiting generator along with transfer switch from Haugland VI and has requested time extension until Jan. 2026 due to generator lead time.

Generator Installation

Curriculum Center

St. Thomas

In progress

2/19/2025 Installation is 90% completed. Contractor is awaiting a replacement computer board from the manufacturer.

Generator Installation

Julius Sprauve

St. Thomas

In progress

2/19/2025 Contractor was paid for Mobilization along with Bonding. Contractor has started civil work during the Christmas shutdown. Contractor is requesting to extend time to the end of Summer 2025.

Generator Installation

Guy Benjamin

St. Thomas

In progress

2/19/2025 Contractor has begun working on the Generator installation. Contractor is 60% completed but is still awaiting the transfer switch. Contractor has also submitted PE #1.

Generator Purchase and Installation

Pearl B. Larsen

St. Croix

In progress

2/19/2025 P&P chaired the pre-construction meeting on 2/18/2025.

Electrical Upgrade

Joseph Gomez

St. Thomas

In progress

2/19/2025 Contractor has requested an extension for time in regard to this project. A lot of the civil work has to be done during the summer and it will shut down the entire school. A change order for time extension was submitted to DPW. Goal is to have project done by the end of Summer.

Electrical Upgrade

Ivanna Eudora Kean

St. Thomas

In progress

2/19/2025 Periodical Estimate No.1 has been submitted and is currently down by DPW. Contractor is working every day and doing as much work as they can without disturbing Schools operation. Contractor has also requested time to complete civil work. This will require shutting down parts of the school over the summer break.

Electrical Upgrade

Jane E. Tuitt

St. Thomas

In progress

2/19/2025 Contractor received the Purchase Order on 12/11/24. Haugland VI has decided to Sub out the work so we can complete this project in a timely matter. Contractor has requested additional time for this project.

Electrical Upgrade

Eulalie Rivera

St. Croix

In progress

2/19/2025 Contractor is 50% done with this project. Contractor is requesting extended time for this project. Goal is to have project done by the end of Summer. PE #1 has also been submitted.

Electrical Upgrade

Juanita Gardine

St. Croix

In progress

2/19/2025 Contractor is waiting to begin work in the summer. This job consists of taking down the schools entire switch gear and main distribution panel. Work can only be done during summer break.

Electrical Upgrade

Lew Muckle

St. Croix

In progress

2/19/2025 Contractor has received mobilization payment and updated drawings along with permits from DPNR. Contractor is waiting on electrical panels etc. to being work. Contractor will need to work during the summer in order to complete project and will be requesting a time extension.

Generator Purchase and Installation

Eulalie Rivera K-8

St. Croix

In progress

P&P chair the pre-construction meeting on 2/18/2025 to begin the project.

Tennis Court Resurfacing

St. Croix Educational Complex

St. Croix

In progress

90% completed completion expected by February 28, 2025.

Auditorium lighting

St. Croix Educational Complex

St. Croix

Completed

Completed

Roof Repairs

SPED

St. Croix

In progress

2/19/2025 Installation of new screws and joint sealing completed. Final roof coating pending completion.

Tiling in Kitchen, Office

Ricardo Richards

St. Croix

Completed

Completed

Repair and or Install Perimeter Fences at Various Public School, St. Croix.

Pearl B. Larsen, Ricardo Richards, Alfredo Andrews, Eulalie Rivera, Lew Muckle, John H. Woodson, Claude O. Markoe, Juanita Gardine, CTECH, Central HS,

St. Croix

In Progress

2/19/2025 % Completed: Woodson 100%, Alfredo Andrews 90%, Pearl B. Larsen 60%, Juanita Gardine 60%, Lew Muckle100%, Ricardo Richards 25%, Central High 50%, Education Complex 50%, Eulalie Rivera and Claudo Markoe 0%

Bathroom Renovations

Central High

St. Croix

On hold

2/19/2025 Project on hold due to expired contract.

Schools Air Quality Assessment (Modulars Only)

STX; Arthur Richards, Central HS, Eulalie Rivera, Pearl B. Larsen, Lew Muckle, STT/STJ; Ivanna E. Kean, Joseph Gomez, Yvonne Milliner-Bowsky, Lockhart K-8, Julius Sprauve, Charlotte Amalie

Territorial

80% Completed

2/19/2024 School Air Quality Assessment Reports have been completed and submitted to BSCM. Preparation of remediation and repair scope in progress.

LED Outdoor Electronic Signage Boards

Ulla F. Muller ES, Jane E. Tuitt ES, Lockhart ES, Yvonne Milliner-Bowsky ES, Joseph Sibilly ES, Joseph Gomez ES, Bertha Boschulte MS, Ivanna E. Kean HS, Charlotte Amalie HS, Julius Sprauve, Ralph O Wheatley Skill Center and Day Adult Center, Edith Williams Alternative Academy

St. Thomas/ St. John

In progress

2/19/2025 Contractor has installed and powered up all signs. A contract extension was given to resolve the internet connection issues. VIDE will have to connect the signs to their servers or have it contracted out.

Surveillance Camera Installation

Charlotte Amalie HS, Julius Sprauve, Joseph Sibilly ES, Uller Muller ES, Yvonne Milliner-Bowsky ES, Edith Williams Alternative Academy, Joseph Gomez ES, Bertha C. Boschulte MS, Addelita Cancryn Intermediate School, Ivanna Eudora Kean HS

St. Thomas/ St. John

In progress

2/19/2025 Phase 3 out of 6 has been completed. The infrastructure, cabling and switches were installed at most Elementary schools. We're currently working at BCB, Kean and CAHS infrastructure. The installation of the cameras will be a part of the last phase.

Gymnasium lighting

St. Croix Educational Complex

St. Croix

In progress

2/19/2025 Contractor awaiting bulb order to complete project.

Fencing at Various Schools

St. Thomas/ St. John

In progress

Revised contract and Notice to Proceed issued on 2/19/2025 by VIDE's Procurement Division.

Interior and Exterior Painting Services

Julius Sprauve and Yvonne E. Milliner-Bowsky

St. Thomas/ St. John

Completed

2/19/2025 All work outlined in the Contract Task Order was completed and inspected.

Interior and Exterior Painting Services

Josph Gomez, Bertha C. Boschulte and Ivanna Eudora Kean

St. Thomas

Completed

2/19/2025 All work outlined in the contract Task Order was completed and inspected. Final payment was submitted and pending issuance.

Interior and Exterior Painting Services

Ulla F. Muller Elementary School

St. Thomas

Completed

2/19/2025 All work outlined in the contract Task Order was completed and inspected. Final payment was submitted and pending issuance.

Purchase and Installation of Pedestrian Crosswalks and Signage

Pearl B. Larsen, Juanita Gardine, John H. Woodson, Alfredo Andrews, Central HS, St. Croix Educational Complex, Eulalie Rivera, Claude O. Marko, Lew Muckle, Montessori School in Rattan.

In progress

2/19/2025 Sign approvals issued. Purchasing of signage is in progress. Upon receipt of signage crosswalk marking and sign installation will commence. This project is jointly managed by BSCM and DPW.